The project timeline: bars, dependencies, critical path, automatic rescheduling, baseline, milestones, absences and export.
The Gantt tab draws the project's work on a time axis. It needs the Gantt module. What lands on the axis is anything with dates: work items with a start or a due date, sprints, releases and milestones.
Read the chart
- Zoom with Days, Weeks, Months or Quarters, the minus and plus buttons, Fit to screen and Today
- Group by parent (a tree), sprint, assignee, status, type or epic; Expand all and Collapse all
- Filter by assignee, type, status or sprint, or Hide finished
- The table beside the bars can show start, end, duration in working days, progress, estimate and variance
- Items without dates stand in the group Not scheduled, which Show unscheduled shows or hides; drag across an item's empty row to give it dates
- A parent's bar comes from its sub-items; dragging it moves the whole branch
Changing dates
Drag a bar to move it and pull its edges to change start or end. With the keyboard: focus a bar, Space picks it up, the arrows move it, Shift pulls the end, Alt the start. Undo reverses the last move.
Dependencies
- Point at a bar and draw an arrow from the circle at its start or end.
- Click the bar it leads to.
- Click the arrow to change its kind or Lag in days, or Delete arrow.
Kinds: finish to start, start to start, finish to finish and start to finish. A dependency the dates do not keep is drawn red. Critical path highlights the items whose delay moves the project's end; other items show how much slack they have.
Automatic rescheduling
Automatic rescheduling decides what happens to the work that waits when you move a bar:
- Never: nothing follows; a broken dependency turns red and you decide. Straighten the chain fixes it on request
- Ask: the chart shows what would move and by how many days, and waits for your yes
- Always: the chain follows at once
Baseline
Choose Capture the plan to keep today's dates as a baseline. Bars then show the promised plan underneath, and how many days later or earlier than promised each item is.
Milestones, working days and absences
- Milestones are kept in the project's Releases tab (New milestone, with a name and a date) and drawn on the axis. Draw a line down the chart highlights one
- Durations count working days. Holidays and sick leave of the assignee show on their rows
Export
Export offers MS Project (XML), Table (CSV) and Picture of the whole plan (PNG).